- Rain on Friday, May 6, 2022 prevented the paving of the street gutter in front of the library. This will be done next week.
- The sidewalk and parking will be accessible over the weekend – please visit the restaurants and shops of SoBro this weekend!
- Vault work at 73 S. Broadway has been completed, no further work scheduled there until the sidewalk gets poured.
- Monday, 5/9, A-Tech will begin excavation of the curb from Hudson Avenue to Maura’s Restaurant.
- Monday, 5/9, A-Tech will begin work on the vault in front of Pizza Bistro. Access will be maintained to the businesses.
- Once curb is excavated, work can begin on excavating sidewalk (takes about a week and a half) and then moving on to new sidewalk cement, followed by paving the street gutter line.
- The full process of the new sidewalk construction can take a couple of weeks, and can be impacted by weather and cement suppliers.
- In the meantime, work will progress in the vaults on the west side of S. Broadway, one by one.
- Village staff is meeting with contractors and inspectors daily for updates and conducts a full project review every other week.
- This update is published on the village website. Follow the project here.